INTERIM FINAL TECHNICAL REPORT
September 1, 1996, through August 31, 1997
Project Title: DEVELOPMENT AND DEMONSTRATION OF A NEW APPROACH FOR
WASTE COAL SLURRY MANAGEMENT USING NATURAL RESOURCE UTILIZATION
BY-PRODUCTS
Principal Investigator: Dr. Y. P. Chugh, Southern Illinois University at Carbondale
Other Investigators: Dr. D. Dutta, Dr. S. Esling, and Dr. B. Paul, Southern Illinois University at Carbondale
Project Manager: Mr. Richard Shockley, ICCI
ABSTRACT
Dr. Chugh recently proposed an alternative approach for management of fine
coal waste slurry (-28 mesh) involving natural resources utilization (coal
burning power plants, limestone processing plants, cement plants, etc.)
by-products. The approach involves formulating environmentally-benign products
with characteristics suitable for mine reclamation. The proposed approach
has significant merit over the current practice and can result in considerable
savings for coal and electric utility companies. This two-year (Phase I)
cooperative project, between coal companies, electric utilities, and the
Coal Combustion Residues Management Program (CCRM) at SIUC, has developed
the approach scientifically and performed small scale (100-200 ton)
demonstrations for five (5) mixtures at two mine sites in Illinois.
In the first year of the project (September 1, 1995 - August 31, 1996), raw
materials were procured from two coal companies, four utility companies and
one limestone processing plant (lime waste). Physical and environmental
properties of the raw materials were studied in laboratory prior to the
development of mixes for the surface demonstration.
Mixing and pumping systems for the field demonstration were investigated
and six test cells were filled at two mine sites during November/December,
1996. Environmental properties of the grouts in the test cells were studied
and compared with the laboratory-prepared grouts. It was found that a good
correlation exists between the laboratory prepared grouts and the grouts
placed in the test cells at the two mine sites. Though not a scope of this
project, limited study indicates that potential exists for growing crops
in these engineered soils without using any natural top soils. A thorough
hydrogeology study of the two demonstration sites was conducted and groundwater
monitoring at two sites was initiated before the placement of by-products-based
mixes in the demonstration pits. To date, samples collected from the monitoring
wells reveal no impact of the test pits on ground water quality at either
sites.
"Pages 1 to 26 contain proprietary information"
EXECUTIVE SUMMARY
Fine coal slurry waste (-28 mesh) from processing plants constitutes
about ten to twenty percent (10-20%) of the run-of-mine coal. It is estimated
that coal operators currently spend between five and eight dollars per ton
of slurry waste. The current disposal technology of pumping a
relatively-low-solids-content (5-15%) slurry into leveed ponds presents long-term
environmental problems related to ground water contamination, acid drainage
and the stability of impounding structures. The coal burning power plants
and other natural resource utilization industries, such as limestone processing
plants and cement plants, similarly produce low or zero value byproducts
which are alkaline and pose long-term environmental problems similar to slurry
waste disposal. The disposal cost for these by-products currently varies
between five and ten dollars per ton and is expected to increase further
over the next decade.
The Principal Investigator (PI) recently proposed an approach to develop
environmentally benign mixtures involving coal slurry waste and natural resource
utilization by-products. The developed mixes may be used in conjunction with
disposal of coarse coal refuse or deposited in coal refuse embankment ponds.
A preliminary economic evaluation of this alternative estimated the cost
to be $2.27/ton, excluding transportation costs of CCBs, which is significantly
lower than disposal cost of slurry alone ($5-8/t) or CCB alone ($8-10/t).
This cooperative research and demonstration project between coal companies,
electric utilities, and CCRM program at SIUC was initiated to further develop
and demonstrate the concept. During September 1, 1995 to August 30, 1996,
extensive laboratory studies were conducted to identify seven mixes suitable
for surface demonstration. The raw materials for the mixes were coal slurries,
fresh F type fly ash (PCC and cyclone boilers), ponded F-type fly ash, fly
ash stabilized and forced oxidation scrubber sludge, FBC fly ash, and lime
waste. Forty three (43) combinations of different by-products were investigated
for their strength, flow and environmental properties and seven final mixes
were selected for field demonstration. However, only five different mixes
could be demonstrated in the field due to the unavailability of ponded fly
ash and fly ash stabilized scrubber sludge.
Two sites were selected for the field demonstration--Marissa mine of Peabody
Coal Company and Crown III mine of Freeman United Coal Company. A thorough
hydrogeology study of the two demonstration sites was conducted and groundwater
monitoring wells were installed and wells were prepared for monitoring impacts
of surface placements of byproducts-based mixes on the groundwater.
Three test cells (20 ft x 20 ft x 8 ft) at Marissa were filled during November, 1996. A field demonstration of materials mixing and pumping was held for representatives of funding agencies and cooperative organizations on November 21, 1996. The project team successfully demonstrated mixing materials in a concrete truck and in a large pit and pumping of 5.75 inch slump grouts over a distance of 250 ft using a concrete pump.
At Crown III mine, two shuttle cars (at right angle to each other) were used
to blend coal slurry, FBC fly ash, F-type fly ash, and scrubber sludge. The
blended materials were taken to the test cells using a two-cubic yard front-end
loader. Water was added in the pit and the blended material was mixed in
the pit using a one cubic-yard back hoe. On December 19, 1996, a second field
demonstration was conducted for representatives of funding agencies and
cooperative organizations at Crown III site. Four (4) cubic yards of blended
material was put in an open-top concrete truck and mixed with water for
approximately 15 minutes. The grout was then pumped to the test cell over
a distance of 280 ft using a concrete pump. A very lean grout of approximately
8-inch slump and a very thick grout of approximately 4-inch slump were pumped
using the same pump.
Grout samples from the field were brought to the laboratory and the
laboratory-cured samples were tested for their compressive strength. It was
found that the strength of the field prepared samples closely matched that
of the laboratory-prepared samples. Grouts collected from the test cells
were tested for their environmental properties. The basic environmental thesis
of this work that individual coal combustion and slurry wastes can be mixed
to produce a material more environmentally safe than any of the components
is now firmly supported by results on both a field and laboratory scale
Groundwater flow at the Freeman site is primarily within a shallow confined
glacial aquifer. The aquifer is bounded below by Pennsylvanian rocks, primarily
shale, and above by Quaternary silty deposits. Nine field tests yield a geometric
mean hydraulic conductivity of 2.9E-5 ft/s (8.8E-6 m/s) for the aquifer.
Groundwater flows through strip mine spoils at the Peabody site. This unconfined
hydrostratigraphic unit is bounded below by Pennsylvanian rocks, primarily
shale. Ten field tests yield a geometric mean hydraulic conductivity of 1.3E-5
ft/s (3.9E-6 m/s) for the spoil. At each demonstration site, two upgradient
wells provide background water quality samples, whereas four wells provide
downgradient water quality samples.
The ambient water quality at the Peabody site is typical of areas impacted
by surface mining. The ambient water quality of the Freeman site shows little
impact from current mining operations. To date, samples collected from the
monitoring wells reveal no impact of the test pits at either the Freeman
or Peabody sites on groundwater quality.
Though not a scope of this project, the PI believes that to reclaim the lands
after disposal of coal slurry and CCBs-based mixes, it is essential to study
the potential of crop growth on these engineered soils without using any
natural top soil. Preliminary study indicates that the potential exists for
growing crops in these soils using foliar feeding technique. Oats were grown
successfully by supplying only iron through foliar feeding. A sufficient
quantity of oat leaves was available for nutrient analysis. Some of the oat
plants were harvested for nutrient analysis while the remainder of the plants
were harvested for grain.
"The remainder of this report contains propriety information and
is not available for distribution except to the sponsors"
OBJECTIVE
The goal of this study is to scientifically develop and perform small
scale (100-200 tons) demonstration of the concept of intimately mixing coal
slurries and natural resources by-products for reclamation and acid mine
drainage control. Specific objectives are to:
1. develop physical and chemical characterization data for fine
coal waste slurry, selected coal combustion by-products and natural resource
utilization by-products that may have potential for co-disposal,
2. develop kinetic reaction rate constants for coal pyrite and alkaline
by-products from coal burning power plants and utilize them to develop mixtures
which will be environmentally benign in both the short-term and the long-term,
3. identify and characterize six (6) environmentally-sound mixes of waste
slurry and by-products which would be suited for mine reclamation at selected
mines,
4. assemble and test equipment for a small-scale demonstration system for
the proposed concept,
5. perform small-scale demonstration studies for three (3) 100-200 ton cells
at each of two mines utilizing identified environmentally-sound mixes,
6. assess the performance and environmental impacts of developed mixes disposed
in cells, and
7. assess the performance of small-scale demonstration equipment.
Objectives 1 to 4 were intended to be accomplished in the first year of the
project. Objectives 5 through 7 are intended for the second year of the project.
In the first year of the project, objectives 1 through 4 were accomplished
successfully. Different tasks that are scheduled to meet the current year's
objectives are:
8. conduct field demonstration of mixing and pumping of grouts at two mine
sites and fill at least three test cells at each mine site,
9. evaluate different mixer-pump combinations and/or mixing methods for small
scale field demonstrations,
10. monitor groundwater after filling the test cells with the grouts,
11. monitor curing characteristics of the grouts placed in the test cells,
12. propose a viable commercial system based on the field experience.