INTERIM FINAL TECHNICAL REPORT
September 1, 1997,
through October 31, 2000
Project
Title:
UNDERGROUND PLACEMENT OF COAL
PROCESSING WASTE AND COAL COMBUSTION BY-PRODUCTS BASED PASTE BACKFILL FOR
ENHANCED MINING ECONOMICS
ICCI
Project
Number:
97US-1
Principal
Investigator:
Dr. Y. P. Chugh, Southern Illinois University at
Carbondale
Other
Investigators:
Dr. D. Deb and Mr. Greg Deaton, SIUC
Project
Manager:
Ronald H. Carty, ICCI
ABSTRACT
The concept being investigated in this project
is that the extraction ratio in a room-and-pillar panel at the cooperating
mine can be increased from current values of about 56% to about 64% and
backfilling can be done from the surface upon completion of all mining activities
in a set of rooms and withdrawal of all equipment without significant ground
control problems due to increased extraction
ratio. The pillars are designed
for short-term stability of 1-2 years.
The mined-out areas are backfilled from the surface with gob, coal
combustion by-products (CCBs)-, and fine coal processing waste (FCPW)- based
backfills containing 65%-70% solids to minimize short-term and long-term
surface movement risk. This
concept has the potential to increase mine productivity, reduce mining costs,
provide a beneficial use for large volume CCBs, and improve the environment
and mine health and safety.
For the purpose of the demonstration, Crown III
mine of Freeman United Coal Company developed a small panel (hereafter called
the backfilling panel) with eight entries with 80 ft by 60 ft (center-to-center)
pillar sizes and 20 ft entry width.
Secondary mining was done in this panel to increase the extraction
ratio from 50-55% to 65%.
Two injection holes were drilled over the study
area to inject coal processing waste and coal combustion by-products into
the panel. For this purpose,
a plant was built to mix about 14% F-ash, 53% FBC and 34% gob with water
for pumping underground.
Underground backfilling was started on August 11, 1999 through the
primary borehole and subsequently on October 13, 1999 through the secondary
borehole. Altogether 9,293 tons of material were injected underground
and it flowed in all directions from the point of
discharge. A maximum flow distance
of 300 ft was observed underground.
Borehole camera survey of the second hole conducted
on September 18, 2000 showed that no new roof falls occurred in the cross
section. On September 27, 2000,
backfill operation resumed through that borehole with F ash and FBC ash are
solid components. A high-speed
auger mixer is being used to mix solids with
water. As of October 30, 2000,
about 6,000 tons of grout was injected
underground. It is estimated
that a total of about 900~1,000 ft of mine voids could be filled during this
phase of backfilling operation.
This estimate will increase as more grout is injected
underground.
EXECUTIVE
SUMMARY
In order to maintain a healthy high sulfur coal
industry in the U.S. and the Illinois coal basin, production costs must be
reduced and economically viable management technologies for coal combustion
by-products (CCBs), fine coal processing waste (FCPW) and coarse coal processing
waste (gob) must be developed.
Over the past decade considerable research has been done in Illinois
on high volume, low value disposal/utilization technologies (disposal in
surface mines, reclamation, disposal in abandoned underground mine
workings). However, little or
no work has been done to beneficially use these by-products in large volumes
to enhance the economics of mining coal and power generation.
About 70% of the underground mined coal (30 to
35 million tons) in Illinois is mined using the room-and-pillar mining method
which permits extraction of only about 50% of the
coal. The remaining coal is
left behind in the form of support pillars to control surface and subsurface
movements. Typically, power
plants in Illinois in rural settings are presently spending $5 - $10/ton
to dispose of CCBs on-site in ponds and this cost is expected to grow rapidly
in light of new requirements for landfill
sites. If coal companies could
negotiate coal contracts with electric utility companies which will reduce
their CCBs management costs and cover the cost of underground backfilling
and transportation, the hypothesis for partial extraction mining with backfilling
is economically feasible.
Implementation of this technology will result in strengthening the
high sulfur Illinois coal industry and keeping the coal industry jobs in
Illinois while providing a secure source of coal supply to power plants from
their backyards.
The concepts being investigated in this project
are that 1) the extraction ratio in a room-and-pillar geometry at the
demonstration mine can be increased from current values of about 56% to about
64%, and 2) the mined-out areas can be backfilled from the surface with FCPW-,
gob-, and CCBs- based backfills containing 65%-70% solids that will minimize
short-term and long-term surface movement and acid-mine drainage
potential.
Crown III mine of Freeman United coal company
is currently mining 600 ft wide panels with 11 entries on 60 ft centers with
20 ft wide entries, and extraction ratio of 50% to
55%. Coal is extracted from No. 6 coal seam at a depth of 300
to 350 ft. The panels vary in
length from 3,000 ft to 5,000 ft.
Seam height is seven feet and the weak floor is composed of 2 to 4.5
ft weak claystone. The dip of the floor is 1.6% in the South East direction
of the panel.
The mining company developed a small panel (hereafter
called the backfilling panel) with eight entries and 80 ft by 60 ft pillar
sizes (center-to-center). The
entry width in the backfilling panels was 20
ft. Secondary mining was done in this panel to increase the
extraction ratio to 65% from 50% to 55%.
In November 1997, three rows of pillars in the backfilling panel were
extracted to a depth of 20 ft by two cuts of 18 ft wide in each
pillar.
Roof-to-floor convergence and surface subsidence
data were collected periodically.
Measurements taken on March 23, 1999, in the backfilling panel indicated
about 1.8 inches of convergence at the center of the
panel. Roof falls were observed
in a few intersections and as a result some of the measuring stations were
destroyed. Due to this reason
and also due to safety concerns, no underground measurements were taken after
that date. However, surface
deformation was measured periodically and it was found that, on an average,
surface deformations were about 1.16 inch over the last one
year.
Two injection holes were drilled to inject backfill
material in the panel. A mixing
plant was built to mix gob, FBC, and F-type ash with
water. Several preliminary mixes were developed using gob and
fluidized bed combustion (FBC) fly ash and
F-ash. Their engineering properties
were documented in a previous report (Chugh et al, 1998).
Due to the strike at Crown III mine, no progress
was made in the field demonstration of underground backfilling until February
1999. However, the Steering Committee met on April 15, 1999 at Crown III
mine and finalized the work plans for this year. Two mixes were selected
for underground demonstration purpose, one having 25% gob and the other having
40% gob in the mix.
Underground observation
in March and borehole camera survey by OSM on July 7, 1999 showed that both
the holes were open for backfilling.
In the primary hole, the camera was lowered to the mine floor level
and the distances of coal pillars from the borehole were
measured. There was a roof fall in the secondary (alternate) borehole
area. However, it was found
that the entries in three directions were open from that
borehole.
In order to demonstrate the flow characteristics
of mixes a trench was dug on the surface with two perpendicular
crosscuts. The trench was about
100 ft long, 9 ft wide and 6-10 ft deep.
On August 9, 1999, the mix with 40% gob was pumped into this trench
to observe the flow behavior. The
mix flowed in all directions after discharged with little separation of water
and solid components. It was
also found that the mix flowed under the water without much
separation.
After two days of preparation, Phase I underground
placement was started at 7:00 a.m. on August 11, 1999 through the primary
hole and the operation ended on September 8,
1999. About 8,159 ton of mix
was pumped underground through the primary hole (5,873 ton of solid and 2,286
ton of water). The daily average
backfilling rate of mix was 627 tons (452 ton of solid and 175 ton of
water). It was found that the
average water to powder ratio is about
40%. With this ratio, 11-inch slump was
achieved. The average hourly
rate of mix was 117.1 tons/hour (83.5 ton/hour of solid and 33.6 ton/hour
of water). On October 13, 1999
backfilling operation resumed through the secondary
borehole. A concrete pump was
used to pump this mix from the plant site to the hole, a distance of about
250 ft. After four days of
operation, 1134 ton of solid and water (773 ton solid and 361 ton of water)
was dumped underground. Altogether
using both boreholes, 9,293 ton of material was injected
underground.
On August 24, 1999, an underground visit of the
backfilling panel revealed that the mix had flowed a considerable distance
(about 120 ft) as expected. It
was found that the flow pattern was sheet-like and uniform in all
directions. The gradient of
backfilled material underground was 1 ft from the roof in all directions
30-ft from the point of discharge.
In addition, the backfilling operation was continued after that
period. Mining Company staff
visited the backfilled area again and found that the backfill had flowed
300 ft from the primary borehole.
During the early part of October the backfilling panel was sealed
off as per the instruction by MSHA and another underground visit was not
possible.
On September 18, 2000, a borehole camera survey
was conducted again in cooperation with OSM for the second hole to observe
the underground conditions in the vicinity of the
borehole. It was found that
entries in the south, west and east directions are
open. No new roof falls had
occurred in that cross section.
Thus, Phase II backfilling operation resumed on September 27,
2000. This time, a high-speed
auger mixer was used to mix solids and water and then inject them
underground. This mix is composed
of F ash and FBC ash. These
two ashes were premixed with 1 ratio 2 (F to FBC ash) by weight and dumped
into a hopper using a front-end-loader.
Water was added at the rear end of the mixer and grout mix came out
from the front end (borehole side).
As of October 30, 2000, about 6,000 tons of grout were injected through
the secondary hole with an water to powder ratio of
0.47. It is estimated that injected
grout can fill over 140,000 cft of underground
void. This means that grout
may fill 900~1,000 ft of mine voids assuming average entry width and opening
height of 20 ft and 7 ft, respectively.
During this operation several 3x6 inch cylindrical samples were prepared
for obtaining compressive strength and elastic modulus of injected
grout.
During Phase I backfilling operation, many samples
were prepared for testing of compressive strength, elastic modulus, slake
durability, swelling strain and hydraulic conductivity of the
mix. In order to perform a
sensitivity analysis of these results, five new mixes similar to field mix
were prepared in the laboratory by slightly varying the proportion of each
mix component. For each mix,
three (3) samples were prepared to obtain an average
result. It is found that the
average strength and elastic modulus after 28-day curing are 190 psi and
17,960 psi, and those of after 90-day curing are 334 and 40,445 psi,
respectively. For the field
samples, slake durability index ranges from 75 to 89% and for similar samples
prepared in the laboratory, it varies from 79 to
92%. Swelling strain for the field samples is slightly lower
and ranges from 6 to 10% while that of similar samples varies from 7 to
15%. For testing hydraulic
conductivity, samples could not be prepared at Crown III mine site but the
similar samples were made in the
laboratory. It shows that for
pressure head between 30 to 50 psi, hydraulic conductivity varies from 0.01
to 0.06 inch/day. It means that
the backfilled material underground is not a permeable
layer.
ASTM shake test was performed for the field mix
and found that the mix was environmentally
benign. The pH of the mix is
11.23 with a Ca concentration of 669 ppm in 1540 mg/l of dissolved
solid. The concentration of
most of the heavy trace elements is below the Class I ground water (GW)
standard.
Strength and elastic modulus data from laboratory
and field samples were analyzed using linear regression
models. It is found that the
ratio of proportion between FBC ash and water content is the most important
parameter for determining 7-day and 28-day cured strength and elastic modulus
of mixes. The ratio between
F ash and FBC ash also plays an important role in estimating 7-day compressive
strength. These relationships
are verified with the samples (similar to field sample) prepared in the
laboratory. This analysis provides
a mathematical foundation for forecasting strength and elastic modulus of
samples composed of FBC ash, F-ash, gob and
water